Home   •   About Medina   •   Medina News   •   Construction Update - Week of October 9th

Medina News

Construction Update - Week of October 9th

Friday, October 6, 2017

North Court Street (US-42) Update:

  • Top course paving will begin from just south of Reagan Parkway moving toward the end of the project.  Tentative start date is Wednesday, October 11th but may change due to potential weather issue
  • Wal-Mart front entrance is currently closed for curb and gutter placement
  • Hillview Way - permanent seeding and mulching will start
  • Crews will begin construction of new Giant Eagle and Medina Shopping Center entrances, including Walgreens' new driveway
  • Concrete crews will continue to place the curbs and gutters in various locations, including building driveway aprons and curb islands
  • East and West Reagan Parkway -  permanent seeding and mulching will continue
  • US-42 from Reagan Parkway to the north end of the project has been completed with intermediate course asphalt
  • Ledgewood Drive and the entrance between Applebee's and Panera Bread is re-opened